06/12/2026
6 Mile Outpost Weekly Update
This week has been focused on a lot of important behind-the-scenes progress as we continue preparing the site for the next major phases of construction.
Crews are finalizing security wiring and electrical Smurf pipe throughout the building, while also preparing to pour the curbs around the property. We also poured the concrete for the front porch, marking another visible step forward.
Work continues on the fire suppression system, including preparations for the installation of a 75,000-gallon cistern that will serve the building’s fire protection needs. The main water line has been run, and we are getting ready to begin construction of the pump house that will support the fire suppression system.
Looking ahead, we are excited to see the front glass installed over the next couple of weeks. Once the building is secured, we will be able to begin internal framing and continue bringing the Outpost to life.
See you at the Outpost!